Mod7Unit8

Module 7 · Unit 8 of 8

Module 7 knowledge check

Six questions across the full module. Take your time — there is no time limit and you will see detailed feedback after each answer.

This knowledge check covers:

  • Unit 1 — Foundations: CM and CA roles
  • Unit 2 — Reading your contract and building the CMP
  • Unit 3 — Relationship management
  • Unit 4 — Managing consulting services contracts
  • Unit 5 — Managing goods and non-consulting services contracts
  • Unit 7 — Amendments, underperformance, and closeout
How this works

Two questions per screen. Both must be answered before you can continue. Your score and question-by-question results are shown at the end.

Module 7 · Unit 8 of 8

Questions 1 & 2

Question 1 of 6 — Unit 1

A CA issues a contract amendment without consulting the CM about whether the proposed additional scope is technically sound. What role boundary has been crossed?

Question 2 of 6 — Unit 2

A CM builds their CMP but does not include a contract calendar. Three months in, the performance security lapses because neither the CM nor the CA noticed the expiry date. Which CMP component was missing and what was its purpose?

Module 7 · Unit 8 of 8

Questions 3 & 4

Question 3 of 6 — Unit 3

A consultant’s progress reports are increasingly brief and uniformly positive. The delivery schedule shows the contract is two weeks behind. How should the CM interpret this, and what should they do?

Question 4 of 6 — Unit 4

Under a lump sum consulting contract, can a CM certify payment based on the consultant’s invoice alone, if the CM already has a good general sense of the work from recent conversations?

Module 7 · Unit 8 of 8

Questions 5 & 6

Question 5 of 6 — Unit 5

Goods are delivered on a Monday. The contract requires the MCA to inspect and formally accept or reject within 10 days. The CM completes the inspection on day 9 but does not issue the formal acceptance notice until day 14. What is the contractual risk?

Question 6 of 6 — Unit 7

A modification to a USD 3 million contract increases the contract value by USD 400,000 — approximately 13% of the original value. What level of approval is required before the amendment is issued?

Module 7 · Unit 8 of 8

Module 7 complete

/ 6
Complete the questions to see your score
1
2
3
4
5
6
Module 7Contract Management Training — 8 units
Units 1–3Foundations: CM–CA roles, reading the contract and building the CMP, relationship management
Units 4–6Consulting services · Goods and NCS · Works contracts (FIDIC)
Unit 7Amendments, underperformance, and closeout
NextModule 8 continues the MCA program lifecycle